Go back

Build a Floating Deck with TuffBlock

Build a Floating Deck with TuffBlock
By Katie Z.
·
November 23, 2021

Since first appearing on the building scene, instant foundation blocks have been the choice of both professional contractors and DIYers for creating strong, stable foundations. These alternative deck foundation blocks have changed the way raised decks and platforms are constructed, providing a lightweight, easy option that replaces heavy concrete blocks.

TuffBlock by BuildTuff is the world’s fastest growing foundation method, and here you'll learn just how easy building a floating deck is with this popular product. In no time, that bare area in the backyard can be transformed into a go-to outdoor destination.

TuffBlock

TuffBlock is more than just an instant deck foundation system—it's a versatile utility block that can be used for a number of various applications, including walkways, sheds, landings, dog shelters and, yes, floating decks. No matter the project, the benefit of TuffBlock is clear: No more digging holes and pouring concrete!

TuffBlock Facts

  • TuffBlock is the lightest deck foundation system on the market.
  • TuffBlock earns its name: Weighing only 1.5 pounds, a single TuffBlock can support over 1,700 pounds.
  • Each TuffBlock repurposes the equivalent of 295 bottle caps—that's something to appreciate next time you're uncapping a bottled water.

TuffBlock Deck Supports

TuffBlock Features

  • Made of high-strength recycled plastic with a high UV rating
  • Ventilated underside prevents moisture buildup and deters termites
  • Blends into landscape and surroundings with a slim profile and satin black finish (unlike unsightly concrete blocks)
  • Accepts 3.5" x 3.5" or 4" x 4" posts and 1.5" - 2" joists and bearers for both low-profile and raised decks
  • Can be secured to the post or bearer for added stability (aTuffBlock exclusive)
  • Will not chip, crack, corrode, or grow mold and comes with a 25-year warranty

Check out the video below to learn more about TuffBlock and get answers to commonly asked questions.

 

How to Build a Floating Deck with TuffBlock Foundation Blocks

As always, be sure to check your local building codes and guidelines before starting your TuffBlock project.

Step 1: Place the two corner TuffBlock piers closest to an existing structure

Place the TuffBlocks directly on the ground. If the ground is sloped, remove top soil from directly underneath the block until the block sits level. If the deck is going to be an extension of an existing structure, then the blocks should be as close to the structure as possible. Ensure the blocks are correctly spaced. The outside edge of the finished deck will extend out past the center of the TuffBlock piers by 350mm (14 inches) on both sides.

Don’t spend an excessive amount of time leveling the TuffBlock piers. The block can be leveled with only your eye. Any slight difference will be made up with the post. However, you want to make sure the TuffBlock piers are sitting flat. You do not want any rocking of the piers on the ground.

Place the two corner TuffBlock piers

Step 2: Level the floor joist

Locate the highest TuffBlock pier. Position a floor joist in or above this first block to your desired height. If the entire deck will be elevated, you will need to have a post in the first TuffBlock.

Place a floor joist in the slot of the TuffBlock pier or on the post and extend over the second corner TuffBlock pier. Now, using a level on top of the floor joist, measure the distance from the top of the floor joist to the bottom of the pocket in the TuffBlock pier. Next, cut a post to length allowing for B-B and position the floor joist on top. Make sure to verify that the floor joist is level. Do not attach the floor joist to the post yet.

If the entire deck is to be elevated, you will first need to establish the height of the first post. Once this is completed continue following the directions above.

Level the floor joist

Step 3: Position and level remaining corner TuffBlock piers

If building off an existing structure, measure from the structure to the outside edge of the post. (For example: If the deck will be 3 meters / 10 feet deep, position the block so that the outside edge of the post is 3 meters / 10 feet from the structure.) Do NOT use the the first row of blocks as a measuring reference. Use the same width between the TuffBlock piers as the first row.

Position remaining corner TuffBlock piers

Step 4: Position and level remaining corner TuffBlock piers

Next, remove the first floor joist closest to the structure. Temporarily position a trim board on top of the first row’s post or block and extend it to the outside corner block. Using a level on top of the trim board, measure the distance from the top of the trim board to the bottom of the pocket on the TuffBlock pier. Cut a post to length. Verify the trim board is level. When level, remove the trim board and repeat for the opposite side.

Level corner TuffBlock pier

Step 5: Place the two corner TuffBlock piers closest to an existing structure

Place the TuffBlocks directly on the ground. If the ground is sloped, remove topsoil from directly underneath the block until the block sits level. If the deck is going to be an extension of an existing structure, then the blocks should be as close to the structure as possible. Ensure the blocks are correctly spaced. The outside edge of the finished deck will extend out past the center of the TuffBlock piers by 350mm (14 inches) on both sides.

Don’t spend an excessive amount of time leveling the TuffBlock piers. The block can be leveled with only your eye. Any slight difference will be made up with the post. However, you want to make sure the TuffBlock piers are sitting flat. You do not want any rocking of the piers on the ground.

Place the two corner TuffBlock piers closest to an existing structure

Step 6: Attach remaining floor joists

Position and attach the remaining floor joists to the trim boards using two 75mm (3-inch) countersunk batten screws to attach the floor joist to the trim board.

Attach remaining floor joists

Step 7: Position remaining TuffBlock piers

Using the frame as a guide, position the remaining TuffBlock piers directly beneath the frame. The blocks on the perimeter of the deck should be 300mm (12 inches) in from each end. When positioning the blocks, the dimensions do not need to be exact; however, do not exceed the maximum span of 1.5 meters (5 feet) between blocks. Be sure to have all of the TuffBlock piers aligned in a straight row and spaced evenly.

Position remaining TuffBlock piers

Step 8: Fill the remaining posts

Cut posts to length and position them between the floor joist and the TuffBlock pier. Repeat this step until all posts are cut and positioned. Next, secure all floor joists and posts using two 75mm (3-inch) countersunk batten screws.

Fill the remaining posts

Step 9: Attach the decking

Starting from one side of the deck, attach the first deck board so it’s flush to the edge of the deck. The deck board will overhang the first floor joist closest to the existing structure. Leave a 3mm to 6mm (0.125 to 0.25 inch) gap between the end of the deck board and the edge of the structure. Next, secure the remaining deck boards as per the manufacturer's instructions.

Attach the decking

Check out the video below to see these steps in action:


Claim that backyard space: Get started on your floating deck project with TuffBlock deck supports from DIY Home Center. If you need any help along the way, contact us via chat, phone or email.


Related read: CAMO Block vs TuffBlock vs Deck Blocks

Comments